Dear All
Sunday 30 November is the official end date of our project. I am very pleased to say that
all remaining deliverables have been submitted.
Deliverables
*
There were six deliverables due at M39=30 November 2025. (D1.4; D4.4; D7.3; D8.3; and
D8.4. and D9.3). So as not to overwhelm you (!) I have scheduled emails so that you will
receive D1.4 today and one other deliverable in pdf format, each day next week.
*
In case there are issues, e.g., with opening the pdf files, you can already download them
from this link
here<https://drive.google.com/drive/folders/1WuZZCBlEDVo21m5J6EyvO7WFSKg….
*
Thank you to everyone who contributed to these deliverables.
EU Portal: P2 and Final Project Reporting
You will also likely receive notifications from the EU portal on Sunday, or early next
week that the project has ended, and that it is time to do the S&T and Financial
Reporting.
@WP Leaders:
1.
We have already made a start on the technical reporting. Please double check you have
submitted your parts in this google doc
link<https://docs.google.com/document/d/1jmeuMa3VS18sHQYssvvqtiKq7PILvAv…
before 8 December (Note: due to prioritisation of deliverables, some sections have had a
first review, others not) . If you have not provided your contributions yet, please do so
by 8 December.
1.
Please inform your finance department that they can start preparing the P2 financial
reporting if they wish (from 1 March 2024- 30 November 2025). LNU will come back with more
information on financial reporting in the portal during the week beginning 8th December.
This is because both Marcelo and I are now both on leave until then.
Thank you all for your efforts and hard work in the project, and wishing you all a good
weekend.
Best regards, Shamim