Hi,
To emphasize what Kurosh wrote, this means that CSC can set the
production date for the 10G TeliaSonera link to September 1!
This also means that we will have the Tundra ring up and running before
the Nordunet networking conference - which is an excellent opportunity
to celebrate our joint efforts!
- Vidar
On 12.04.2016 08:25, Kurosh Bozorgebrahimi wrote:
Hi, Here comes a short update from Uninett. In the
past two weeks we
were working with Ishavslink (Owner of the DWDM ring in Finnmark) and
Transmode to finalize the "bill of materials" for the Utsjok OADM. On
Thursday 7th of April we ordered the equipment and Transmode has
confirmed that they will deliver the equipment by the end of May.
According to the plan the upgrading of Utsjok node will happen on Jun
16th. Then we have to connect the 10G link from Alta to Narvik, and
this will be done within June/July. With summer vacation time in mind
the UNINETT part of TUNDRA ring should be ready for service by end of
August. It means that we are ready one month earlier than we decided
under Tundra kickoff meeting. Best regards, Kurosh
_______________________________________________ Tundra mailing list
Tundra at lists.sunet.se
https://lists.sunet.se/listinfo/tundra
--
Vidar Faltinsen <vidar.faltinsen at uninett.no>
Chief Technical Officer / Avdelingsdirektør
Network and Infrastructure / Nett og infrastruktur
UNINETT AS - The Norwegian Research and Education Network
Phone: +47 73 55 78 25 | Mobile: +47 411 26 197